HOLY TRINITY ROMANIAN ORTHODOX CHURCH
SUNLAND PROPERTY: READY TO START BUILDING
April
6, 2005
Dear parishioners & supporters of Holy
Trinity Church,
From the last report regarding the Building
Project, which we have officially given at the 65th Church
Anniversary, followed by the December 2004 issue of the “Viata Crestina”, and
ultimately up-dated and presented to the parish General Assembly of February 6,
2005, the building committee wishes to inform the parishioners, supporters of
our Building Project, and the magazine readers of the following established
schedule:
the
BUILDING PROJECT - Phase I
(Consists of the
below-stated steps):
1. Step I
1.
1.1.
Obtain a “building risk insurance policy”;
1.2.
Pull grading permits
1.3.
Install fire hydrant & water meter
1.4.
Site preparation: overall clearing, grubbing,
temporary fencing, electric & hygiene facilities
1.5.
Survey (grading stakes, pad bluetops, corners
& utilities stakes)
1.6.
Rough grading, over-excavation and
recompaction, cut-fill, for all buildings & parking area
1.7.
Dig trenches and install the underground
utilities.
1.8.
Install the drain system, catch basins,
gutters, curbs
1.9.
Build the retaining walls, backfill and
compaction of retaining walls
1.10.
Foundation and slabs for both buildings: Church
& Hall
1.11.
Fine (finish) grading
1.12.
Off-site street improvements, front-property
trail, lighting & traffic control.
2. Step II
2.1.
Construction of the Church
2.2.
Construction of the Hall
3. Step III
3.1.
Paving the parking areas & driveways
3.2.
Landscaping
3rd building complex - Phase II: offices, Sunday School Rooms, Museum, Quarters.
FOLLOWING MEASURES ARE IN PLACE
I. The
Architects and the Structural Engineers have made and re-submitted the plans’
corrections, as requested by the Building & Safety Department of Los Angeles
(BSDLA), and PRESENTLY we are waiting for ALL THE ARCHITECTURAL PLANS to be
approved.
II. The
“Soil and Geological” Report, as previously stated, was approved by BSDLA.
III. Commercial
kitchen plans are approved by the Health Department
IV. The
Grading Plans were approved by BSDLA.
V.
A Builders Risk Insurance Policy is presently
negotiated with the Mutual Insurance Agency
VI.
Application for Fire Hydrant is in process.
VII.
Construction bids were taken from 10
Construction companies:
a. Phase I - Turn-key project
(3 Estimates)
No. |
Name of the Construction Company |
Estimated Cost |
# 1. |
Gentosi Builders, Inc. – Santa Ana, CA Phase I - Steps I, II & III |
$ 7,010,495.00 |
# 2. |
$ 6,981,581.00 |
|
# 3. |
Gary C. Hopkins Construction, Inc. –
Glendale, CA Phase I - Steps I, II & III Estimate does not include: site underground utilities,
landscaping… |
$ 5,397,387.00 |
B.
Phase I – GRADING,
RETAINING WALLS, CONCRETE
(10 Estimates: Part or All Items
in “Phase
I, Step I”)
No. |
Name of the Construction Company |
Estimated Cost |
# 1. |
Gentosi Builders, Inc. – Santa Ana, CA General Conditions%, Site Work, Concrete (Overhead, insurance & profit % not
included) |
$ 2,321,580.00 |
# 2. |
$ 2,178,723.00 |
|
# 3. |
$ 1,514,709.81 |
|
# 4. |
Gary C. Hopkins Construction, Inc. –
Glendale, CA Rough & Finish Grading ONLY (Phase I -
Step I, 1.6) |
$ 805,720.00 |
# 5. |
Sharma Engineering Contractors – Westlake
Village, CA Rough & finish grading, Phase I – Step I,
# 1.4; 1.6 & 1.9 backfill only; 1:11 |
$ 639,800.00 |
# 6. |
Gerig Construction, Inc.- Thousand Oaks, CA Rough & finish grading, Phase I – Step I
# 1.6 & 1:11 |
$ 485,200.00 |
# 7. |
Michael Adams Trucking & Excavation –
Los Angeles, CA Clearing, Grading - Phase I, Step I # 1.4;
1.6; & 1.11 |
$ 350,000.00 |
# 8. |
Rubin Asheghie Construction – Glendale, CA Clearing, Grading - Phase I, Step I # 1.4;
1.6; 1:9 Trench Work Only & 1.11 |
$ 238,000.00 |
# 9. |
Kayson Construction Co. Joe Sonei – Canoga
Park, CA Clearing, Grading …(estimate unclear) |
$ 225,000.00 |
# 10. |
PRG, Inc - General Engineering Contractors Rough Grading Only - Phase I, Step I # 1.6 Church will make the site preparation (clearing,
grubbing) |
$ 159,675.00 |
A Grading Company has been hired
Desiring not to rush with construction
decisions, for almost 3 months (January-March 2005), the Executive Board of the
Building Committee held various meetings with General Constructor Companies,
Independent Constructors and Sub-Constructors (including Constructors from the
Romanian-American Companies), thus securing 3 “Turn-Key Project” Construction
Bids, and some 10+ Construction Bids, for Phase I, Step I, Items 1.1
through 1.12 from General Constructors and Sub-constructors (as stated above).
With such work in place, at the specially
convoked meeting of Tuesday, April 5 2005, the Executive Board of
the Building Committee (Dorian Serban, John Simoni, Mario Theodorou, Constantin
Jercan & Fr. Constantin Alecse) took the following decisions:
a) Enter into a Contract with PRG, Inc - General Engineering Contractors – For Rough Grading, Phase I, Step I # 1.6. Church
will make the site preparation (clearing, grubbing), for the Estimated amount
of $ 159,675.00, besides all the
Estimate’s exclusions.
b) Apply
for the “Grading Permit” at once.
c) Draw,
review and sign the “Grading Contract” (work & payment schedule) by April
15, 2005.
d) Grading
Constructor made the commitment to start grading within 2-3 weeks from the time
the Contract is signed.
e) Submit
an application for Fire Hydrant, Water & Electric Meters at once.
f)
Hire a brash clearing sub-contractor, to
start clearing the property before the beginning of May 2005.
g) Make
arrangements with the Surveyor (Civil Engineer/Soil Engineer) to:
·
Set the boundary monuments & spot elevations.
·
Implement the horizontal control plan by using the staking
plan for all improvements to the property line.
·
Implement the construction staking and setting of
horizontal and vertical controls, ready for grading.
h) The
Parish Priest and the Building Committee, is grateful (on behalf of the whole parish) to Mr. John Simoni – a California
Licensed, Insured and Bonded General Constructor - who volunteered to
take-up the responsibility of Project Manager/Superintendent, for the “grading
period of time”, with the possibility of extending this “courtesy duty”,
according to various phase’s constructor needs, and other Romanian-American
General Constructors’ involvement.
Immediately after
Orthodox Easter (May 1, 2005), when the “actual physical building-work/grading
will start”, the parish office will detail to the parishioners, supporters and
the whole Romanian-American Community, the work-in-progress schedule
& the appeal of the “Ways & Means Committee”, entrusted with the
Fundraising activities for the Building Program.
Respectfully
submitted,
On
behalf of the Building Committee & the Parish,
Fr.
Constantin Alecse Constantin Jercan
Parish Priest
Building Committee Chairman